Ordering concrete comes down to one number: cubic yards. Get it close, add a small margin, and the pour goes smoothly. Here's how to work it out for the shapes most jobs need.
The formula
Cubic yards = length (ft) × width (ft) × depth (ft) ÷ 27
Concrete is ordered by the cubic yard, and one cubic yard is 27 cubic feet. Depth is usually measured in inches, so divide it by 12 first: 4 inches is 0.333 ft, 5 inches is 0.417 ft and 6 inches is 0.5 ft.
Slabs, patios and driveways
A 12 by 10 ft patio, 4 inches thick:
- 12 × 10 × 0.333 = 40 cubic feet
- 40 ÷ 27 = 1.48 cubic yards
- Plus 10 percent, rounded up to the nearest half yard: 2 cubic yards
| Slab thickness | Cubic yards per 100 sq ft |
|---|---|
| 4 inches | 1.23 |
| 5 inches | 1.54 |
| 6 inches | 1.85 |
Your plans, engineer or local code set the thickness. Patios and walkways are commonly poured 4 inches thick, and driveways are often thicker, but go by the plans for your job.
Footings
For a continuous footing, multiply its width by its depth by its total length. A footing 16 inches wide and 8 inches deep, running 60 ft:
- 1.333 × 0.667 × 60 = 53.3 cubic feet
- 53.3 ÷ 27 = 1.98 cubic yards
Add up every run, including any steps or thickened sections, before you add the margin.
Walls
For a poured wall, multiply its thickness by its height by its length. An 8-inch wall, 4 ft tall and 20 ft long:
- 0.667 × 4 × 20 = 53.3 cubic feet
- 53.3 ÷ 27 = 1.98 cubic yards
Post holes and round piers
For a round hole, use 3.14 × radius × radius × depth, all in feet. A 12-inch hole has a 0.5 ft radius. Ten holes, 12 inches across and 4 ft deep:
- 3.14 × 0.5 × 0.5 × 4 = 3.14 cubic feet per hole
- 3.14 × 10 holes = 31.4 cubic feet
- 31.4 ÷ 27 = 1.16 cubic yards
Subtract the volume of anything set in the hole, such as a post, if it's large.
How much extra to order
Add about 10 percent. Bases are rarely perfectly flat, forms bow a little, and some concrete is always lost to spillage. Running short partway through a pour costs far more than a little left over.
With volumetric delivery, we mix the yardage at your pour and you pay for what's placed, so a margin you don't use doesn't cost you. Our concrete calculator adds the 10 percent and rounds up to the nearest half yard for you.
Bags or a truck?
An 80 lb bag of premix typically yields about 0.6 cubic feet, so one cubic yard takes roughly 45 bags. Check the yield printed on the bag. Past a few bags, mixing by hand gets slow and the batches won't match, which is when a delivered pour makes more sense.
Double-check before you book
- Measure the depth in several spots, not just one. An uneven base can change the total more than you'd expect.
- Split odd shapes into rectangles, work out each one, and add them together.
- Not sure about your numbers? Send us the dimensions and we'll check them before you book. Call (360) 852-6473.
Source: Volumes are standard geometry (1 cubic yard = 27 cubic feet). The 10 percent margin and half-yard rounding match the Natrix concrete calculator.