Dry-stack means no mortar, no forms and no waiting for concrete to cure. Verti-Block units arrive already cured, an excavator sets them, and the wall is backfilled as it goes up.
- 8 sq ftWall face per standard unit, set in one pick
- ~450 sq ftWall face set per crew-day, in our experience
- NoneNo forms, no rebar, no cure time
What you need on site
- Excavator and block grab: a standard unit weighs about 1,760 lb empty, and the heaviest mass extender about 5,100 lb. Every unit has cast-in lift loops.
- Compaction: hand-operated equipment within 3 ft of the wall, larger equipment beyond that.
- Materials: crushed stone for the leveling pad, clean 1 in. crushed stone for the cores, perforated drain pipe and non-woven filter fabric.
- Staging room: each truckload carries 304 sq ft of wall face.
Step by step
- Excavate and prepare the foundation: proof-roll the subgrade, with bearing soils confirmed by the geotechnical engineer and unsuitable soils replaced.
- Build the leveling pad: at least 6 in. deep (12 in. where required), of compacted crushed stone 1 ft wider than the block depth, or 3,000 psi concrete. It must be level and accepted before the first course.
- Set the drain pipe and the first course: the first course goes over the drain pipe and is leveled side to side and front to back. It is the most important course on the wall.
- Fill the cores: clean crushed stone goes in the cores as each course is set.
- Backfill and compact: lifts of 12 in. maximum, with only hand-operated compactors within 3 ft of the wall, with filter fabric where the design calls for it.
- Stack the next course: running bond, with each female notch set over the male riser below and pulled forward to set the batter.
- Finish the top: top blocks or caps, then the finish grade sloped at least 2% away from the wall face.


Where the field labor goes, and where it doesn't
- No forming or stripping, no rebar to cut and tie, and no cure time before backfill.
- Fewer picks: each standard unit is 8 sq ft of finished face.
- Batter set by the block: the male/female connection sets it on every course, so the crew isn't measuring setback course by course.
- Where the hours go: leveling pad and first course, filling cores, and compacting backfill in lifts.
In plain terms Get the first course right and the rest of the wall follows it. Most of the crew's day is filling and compacting, not fussing with alignment.
What affects daily production
In our experience, a crew sets about 450 sq ft of wall face per day. Production drops with tight access or limited staging room, many curves and corners, and geogrid layers that have to be placed and compacted between courses. It is fastest on long, straight runs with room to stage block.
Inspection and quality checks
- Leveling pad accepted before the first course goes down.
- First course checked level side to side and front to back.
- Compaction tested at least every 2 vertical ft and every 50 lineal ft, to the density in the project specification.
- Backfill soils with a liquid limit under 45 and a plasticity index under 20, unless the geotechnical engineer approves otherwise.
Who can install it
Any qualified contractor. There is no exclusive-installer lock-in, so the spec stays open to competitive bids. Natrix can recommend experienced installers and supports whichever contractor wins the job. Full specification points are in the design data, and the installation guide is in the design manual in our design library.
Source: Verti-Crete Design Manual, Release 4.1 (installation guide), Verti-Block product data sheets, and Natrix Precast project experience (marked "in our experience").