The short answer

Verti-Block suits terraced landscapes because each tier can be a short gravity wall, with a top block that lets soil and plants run right to the edge, half-step units that follow the grade, curves down to a 16 ft radius and stairs built into the face. Tiers built close together must be designed as one structure.

Planning data, not a wall design. Every retaining wall needs a site-specific design by a licensed engineer. We draft free preliminary designs, and a licensed PE reviews and stamps the final design on approval.

Verti-Block standard unit: stone-textured face, hollow core and two cast-in lift loops
This is Verti-Block. One standard unit: 2 ft high, 4 ft wide, 3 ft deep, about 1,755 lb.

A terrace turns one tall, steep slope into a series of shorter walls with flat benches between them. The benches become lawn, planting beds, paths or a patio, and each wall stays a more manageable height.

Should I terrace a slope or build one tall wall?

Terrace when one tall wall would go past the height your soil allows as a gravity wall, or when you want level benches for planting or use. Keep each tier a short gravity wall and space the tiers apart. Tiers closer together than about twice the lower wall's height act as one taller wall and have to be designed as one structure. If the full height fits within the published gravity range for your soil, one wall is simpler. Natrix Precast's published tables show Verti-Block gravity walls from 5.5 to 19 ft without geogrid, depending on soil, surcharge and slope; seismic loads are not included. The soil rows and assumptions are in the Verti-Block design data. Heights with a slope behind the wall are in the steep slope guide.

Why terrace a slope

  • Usable ground: flat benches you can plant, walk on and maintain.
  • Shorter walls: each tier can often stay a gravity wall, with no geogrid zone behind it.
  • A softer look: planting between tiers breaks up the height.
Tiered Verti-Block walls stepping up a hillside below homes
Tiers stepping up a hillside.
Verti-Block wall stepping up a slope with planting above
Height steps that follow the slope.
Verti-Block wall with stairs leading up from a modern home
Stairs between levels.

Spacing the tiers

How far apart the tiers sit decides whether they act as separate walls or as one tall one. A common design guideline: if the horizontal distance between two tiers is less than about twice the height of the lower wall, the upper tier adds load to the lower one, and the two must be designed together.

In plain terms Two 4 ft walls sitting close together can behave like one 8 ft wall. Leave a wide bench, or design them as one.

The engineer of record sets the final spacing and checks the global stability of the whole slope, not just each wall on its own.

Shaping each tier

  • Verti-Block top unit with a soil cutoutTopSoil and planting run over the top edge
  • Verti-Block half-step unitHalf-step1 ft height changes that follow the grade
  • Verti-Block corner unit with a finished returnCornerFinished 90° and 45° corners
  • Curves: convex and concave, down to a 16 ft radius, so tiers can follow the contours of the hill.
  • Stairs: built into the wall face to connect the benches.
  • Fences and railings: posts can be set in the hollow cores or just behind the top course.

Drainage between tiers

Water that soaks into an upper bench has to get out without building up behind the wall below. Each tier gets its own drainage: stone in the cores as a full-height drain, a perforated pipe at the base, filter fabric, and benches graded so surface water runs away from the wall faces instead of over them.

Wall section showing the four drainage details: stone core, base pipe, filter fabric and grading

Planning a terraced slope

  1. Send us the slope: a topo or grading plan and where you want the benches.
  2. We draft a preliminary design: tier heights and spacing, block counts and a budget number.
  3. Stamped on approval: a licensed PE reviews and stamps the final design for permit.

For heights, block sizes and weights, see the Verti-Block design data.

Source: Verti-Crete Design Manual, Release 4.1, Verti-Block product data sheets, and Natrix Precast project experience.

FAQ

Common questions

What is the best precast block for terraced landscapes?

Look for a block that builds short gravity walls without geogrid, lets soil and planting run to the top edge, steps with the grade, curves and takes stairs. Verti-Block does each of those: top blocks with a soil cutout, 1 ft half-step units, curves down to a 16 ft radius, and stairs built into the face.

How far apart should retaining wall tiers be?

A common design guideline: if the horizontal distance between tiers is less than about twice the height of the lower wall, the upper tier loads the lower one and the two are designed together. The engineer of record sets the spacing and checks the global stability of the whole slope.

Can plants grow right to the top of a Verti-Block wall?

Yes. The top block has a soil cutout at the back, so soil, grass and planting run right over the top of the wall.

Can a terraced wall include stairs?

Yes. Stairs can be built into the wall face to connect the benches, and 1 ft half-step units let the top of each tier follow the grade.

Should I terrace a slope or build one tall wall?

Terrace when one tall wall would go past the height your soil allows as a gravity wall, or when you want level benches for planting or use. Keep each tier a short gravity wall and space the tiers apart; tiers closer together than about twice the lower wall's height act as one taller wall and are designed as one structure. If the full height fits within the published gravity range for your soil (5.5 to 19 ft without geogrid, depending on soil, surcharge and slope, with seismic loads not included), one wall is simpler.

Do terraced walls need an engineer?

Usually. Tiers that are close together act as one taller wall, and many walls need an engineered design and a permit; your city or county sets the thresholds. Natrix drafts free preliminary designs, and a licensed PE stamps the final design.